Q.: Input  and  output  combinations  that  will  be  treated  the  same  way  by  the  system  can  be  tested  using  which  technique?
A. Boundary  value
B. Equivalence  partition
C. Decision  table
D. State  transition

B is correct
<<<<<< =================== >>>>>>
Q.: Branch Coverage
A. Another name for decision coverage
B. Another name for all-edges coverage
C. Another name for basic path coverage
D. All the above

A is correct
 

<<<<<< =================== >>>>>>
Q.: The _________ Is the activity where general testing objectives are transformed into tangible test conditions and test designs
A. Testing Planning
B. Test Control
C. Test analysis and design

D. Test implementation

C is correct
<<<<<< =================== >>>>>>
Q.: Integration testing where no incremental testing takes place prior to all the system�s components being combined to form the system.
A. System testing
B. Component Testing
C. Incremental Testing
D. Big bang testing

D is correct
 

<<<<<< =================== >>>>>> 
Q.: A test case design technique for a component in which test cases are designed to execute statements is called as?  
A. State transition Testing
B. Static Testing
C. Transition testing
D. Statement testing

D is correct
 

<<<<<< =================== >>>>>> 
Q.: Who should have technical and Business background.  
A. Moderator
B. Author
C. Reviewer
D. Recorder

C is correct
 

<<<<<< =================== >>>>>> 
Q.: A test plan defines  
A. What is selected for testing
B. Objectives and results
C. Expected results
D. Targets and misses

B is coreect
 

<<<<<< =================== >>>>>> 
Q.: Features  to be  tested,  approach  refinements  and  feature  pass / fail  criteria  BUT  excluding  environmental  needs  should  be  specified  in which  document?  
A. Test  case  specification
B. Test  plan
C. Test  procedure  specification
 

D. Test  design  specification
D is correct
<<<<<< =================== >>>>>>
 

Q.: Test basis documentation is analyzed in which phase of testing  
A. Test Analysis
B. Test Design
C. Test Execution
D. Test Planning

A is correct
 

<<<<<< =================== >>>>>> 
Q.: Which one is not the task of test leader? 
A. Coordinate the test strategy and plan with project managers and others
B. Decide about the implementation of the test environment
C. Write test summary reports
D. Review and contribute to test plans

D is correct
 

<<<<<< =================== >>>>>>
Q.: Integrity testing involves:
A. The testing of pseudo code
B. Performance testing
C. Alpha testing
D.The final phase of testing prior to deployment

 D is correct

<<<<<< =================== >>>>>>
Q.: As a  moderator  in a  typical  formal  review, what  can  be  one  of  your  responsibilities?
A. Deciding  on the execution of  reviews
B. Documenting  all the issues  and  problems
C. Leading the  review o f the  documents
D. Identifying  and  describing  the  findings
 
C is correct
<<<<<< =================== >>>>>>
Q.: Which is not a major task of test implementation and execution:

A.  Develop and prioritizing test cases, creating test data, writing test procedures and optionally, preparing test harness and writing automated test scripts.

B.  Logging the outcome of test execution and recording the identities and versions of the software under test, test tools and testware.

C.  Checking test logs against the exit criteria specified in test planning.
D. Verifying that the test environment has been set up correctly.
 C is correct
<<<<<< =================== >>>>>>
Q.: Which of the following is not appropriate for testing interactions between paths?
A.  Path that people are particularly likely to follow
B.  Choices at one menu level or data entry screen can affect the presentation of choices elsewhere
C.  Test reaction to all combinations of valid and invalid inputs
D. Randomly select different paths in each test cycle

 C is correct

<<<<<< =================== >>>>>>
Q.: Which of the following is the main purpose of the component build and integration strategy?
A. to ensure that all of the small components are tested
B. to ensure that the system interfaces to other systems and networks
C. to ensure that the integration testing can be performed by a small team
D. to specify how the software should be divided into components
E. to specify which components to combine when, and how many at once
E is correct
<<<<<< =================== >>>>>>
Q.: Which of the following BEST describes the difference between an inspection and a walkthrough? 

A. Both inspections and walkthroughs are led by the author.
B. An inspection is led by a moderator and a walkthrough is led by the author.
C. Both inspections and walkthroughs are led by a trained moderator.
D. A walkthrough is led by the author. The author is not present during inspections.
B is correct 

<<<<<< =================== >>>>>>  
Q. : Where may functional testing be performed?
A. At system and acceptance testing levels only.  

B. At all test levels.
C. At all levels above integration testing.
D. At the acceptance testing level only.

B is correct
<<<<<< =================== >>>>>>  

Q.: What is the MAIN objective when reviewing a software deliverable?
A. To identify potential application failures by use of a test specification.
B. To identify defects in any software work product.
C. To identify spelling mistakes in a requirements specification.
D. To identify standards inconsistencies in the code.

B is correct
<<<<<< =================== >>>>>>

Q.: As part of which test process do you determine the exit criteria?  
A. Test planning.
B.
Evaluating exit criteria and reporting.
C. Test closure.
D. Test control.

A is correct
 

<<<<<< =================== >>>>>> 
Q.: Which of the following is a MAJOR task of test implementation and execution?  
A. Measuring and analyzing results.
B. Reporting discrepancies as incidents.
C. Identifying test conditions or test requirements.
D. Assessing if more tests are needed.

B is correct
<<<<<< =================== >>>>>>

 
    