Papers Q. 31 to 40


Q.: With which of the following categories is a test comparator tool USUALLY associated?
A. Tool support for performance and monitoring.
B. Tool support for static testing.
C. Tool support for test execution and logging.
D. Tool support for the management of testing and tests
C is correct
<<<<<< =================== >>>>>>
Q.: Which activities form part of test planning?
i) Developing test cases.
ii) Defining the overall approach to testing.
iii) Assigning resources.
iv) Building the test environment
v) Writing test conditions.

A. i, ii & iv are true, iii & v are false.
B. ii & iii are true, i, iv & v are false.
C. iv & v are true, i, ii & iii are false.
D. i, ii & iii are true iv & v are false.
B is correct
 
<<<<<< =================== >>>>>> 
Q.: Match the following terms and statements.
1.Decision Table Testing
2.Decision Testing
3.State Transition Testing
4.Exploratory Testing
W. Testing carried out w boxes to achieve specific test objectives, possibly to complement structured testing.
X. A test technique used which may be used to verify different system re depending on current conditions or previous history.
Y. A test technique which combines combinations of inputs that might not otherwise have been exercised during testing.
Z. A form of control flow testing based on decision outcomes.
 
Options:
A. 1Y, 2Z, 3X, 4W.
B. 1X ,2W, 3Z, 4Y.
C. 1Z, 2X, 3W, 4Y.
D. 1Z, 2Y, 3X, 4W.

A is correct
<<<<<< =================== >>>>>> 
Q.: Which type of test design techniques does the following statement best describe a procedure to derive test cases based on the specification of a component? 
A. Black Box Techniques.
B. White Box Techniques.
C. Glass Box Techniques.
D. Experience Based Techniques.
A is correct
 
<<<<<< =================== >>>>>> 
Q.: For which of the following would a static analysis tool be MOST useful?
A. Supporting reviews.
B. Validating models of the software.
C. Testing code executed in a special test harness.
D. Enforcement of coding standards.
D is correct
 
<<<<<< =================== >>>>>> 
Q.: Which  test  approaches  or  strategies  are  characterized  by the  descriptions  below?
S. Process-compliant  approaches
T. Heuristic  approaches
U. Consultative  approaches
V. Regression-averse  approaches

1. Includes  reuse of  existing  test  material
2. Listens  to suggestions from  technology  experts
3. Adheres  to industry-specific  standards
4. Runs test  execution  and  evaluation  concurrently
 

A. S4, T3, U2, V1
B. S1, T2, U3, V4
C. S2, T3, U1, V4
D. S3, T4, U2, V1
D is correct
 

<<<<<< =================== >>>>>>
Q.: What  principle is  BEST  described  when  test  designs  are  written  by a third party?  
A. Exploratory  testing 
B. Independent  testing
C. Integration  testing
D. Interoperability  testing

B is correct
<<<<<< =================== >>>>>>
Q.: Which of the following is a benefit of test independence? 
A. It does not require familiarity with the code.
B. It is cheaper than using developers to test their own code.
C. It avoids author bias in defining effective tests.
D. Testers are better at finding defects than developers.
C is correct
 
<<<<<< =================== >>>>>>
Q.: Which of the following is MOST characteristic of specification based (black-box) techniques?
A. Test cases can be easily automated.
B. Test cases are independent of each other.
C. Test cases are derived systematically from models of the system .
D. Test cases are derived systematically from the delivered code.

C is correct
 

<<<<<< =================== >>>>>>
Q.: Item transmittal report is also known as
A. Incident report
B. Release note
C. Review report
D. Audit report
B is correct
 

<<<<<< =================== >>>>>>
Q.: COTS is known as
A. Commercial off the shelf software
B. Compliance of the software

C. Change control of the software
D. Capable off the shelf software

A is correct
<<<<<< =================== >>>>>> 

Q.: Change request should be submitted through development or program management. A change request must be written and should include the following criteria. 
I. Definition of the change
II. Documentation to be updated

III. Name of the tester or developer
IV. Dependencies of the change request.

A. I, III and IV
B. I, II and III
C. II, III and IV
D. I, II and IV

D is correct
 

<<<<<< =================== >>>>>>
Q.: Change X requires a higher level of authority than Change Y in which of the following pairs? Change X Change Y
A. Code in development Code in production
B. Specifications during requirements analysis Specifications during systems test
C. Documents requested by the technical development group Documents requested by customers
D. A product distributed to several sites A product with a single user

D is correct
 

<<<<<< =================== >>>>>> 
Q.: Cause effect graphing is related to the standard  
A. BS7799
B. BS 7925/2
C. ISO/IEC 926/1
D. ISO/IEC 2382/1

B is correct
 

<<<<<< =================== >>>>>> 
Q.: The primary goal of comparing a user manual with the actual behavior of the running program during system testing is to  
A. Find bugs in the program
B. Check the technical accuracy of the document
C. Ensure the ease of use of the document
D. Ensure that the program is the latest version

B is correct
 

<<<<<< =================== >>>>>> 
Q.: During the testing of a module tester �X� finds a bug and assigned it to developer. But developer rejects the same, saying that it�s not a bug. What �X� should do? 
A. Report the issue to the test manager and try to settle with the developer.
B. Retest the module and confirm the bug
C. Assign the same bug to another developer
D. Send to the detailed information of the bug encountered and check the reproducibility

D is correct
 

<<<<<< =================== >>>>>> 
Q.: One of the more daunting challenges of managing a test project is that so many dependencies converge at test execution. One missing configuration file or hard ware device can render all your test results meaning less. You can end up with an entire platoon of testers sitting around for days. Who is responsible for this incident?
A. Test managers faults only
B. Test lead faults only
C. Test manager and project manager faults
D. Testers faults only

A is correct
<<<<<< =================== >>>>>>

Q.: You are a tester for testing a large system. The system data model is very large with many attributes and there are a lot of inter dependencies with in the fields. What steps would you use to test the system and also what are the efforts of the test you have taken on the test plan 
A. Improve super vision, More reviews of artifacts or program means stage containment of the defects.
B. Extend the test plan so that you can test all the inter dependencies
C. Divide the large system in to small modules and test the functionality
D. Test the interdependencies first, after that check the system as a whole
A is correct
 
<<<<<< =================== >>>>>> 
 Q.: Testing of software used to convert data from existing systems for use in replacement systems 
A. Data driven testing
B. Migration testing
C. Configuration testing
D. Back to back testing

B is correct
<<<<<< =================== >>>>>>  