Papers Q. 191 to 200



Q.: In a review meeting a moderator is a person who
A. Takes minutes of the meeting
B. Mediates between people
C. Takes telephone calls
D. Writes the documents to be reviewed
B is correct
 

<<<<<< =================== >>>>>>
Q.: Acceptance test cases are based on what?

A. Requirements
B. Design
C. Code
D. Decision table
A is correct
 
<<<<<< =================== >>>>>>
Q.: Which  documents  specify  features  to - be  tested,  approach, and  pass / fail  criteria?
A. Test  plan and  test  design  specification
B. Test  plan and  test  case  specification
C. Test  procedure  specification  and  test  design  specification
 

D. Test  case  specification  and  test  procedure  specification
A is correct
<<<<<< =================== >>>>>>
Q.: Independent Verification & Validation is
A. Done by the Developer
B. Done by the Test Engineers

C. Done By Management
D. Done by an Entity Outside the Project�s sphere of influence
 
 

D is correct  
 <<<<<< =================== >>>>>>
Q.: Defect Management process does not include  
A. Defect prevention
B. Deliverable base-lining

C. Management reporting
D. None of the above

D is correct
 

<<<<<< =================== >>>>>>  
Q. What  is a  group  of  test  activities  that  are  organized  and  managed  together?
A. Test  procedure  specification
B. Test  level

C. Test  case  specification
D. Test  plan

B is correct
 

<<<<<< =================== >>>>>>  
Q.: What is  the  key  difference  between 
(a)  contract  and  regulation  acceptance  testing
(b) alpha and  beta  testing? 
A. (a) are  performed  outside the  company and (b) are  conducted  by the  test team
B. (a) are  conducted  by  regulators and (b) are performed by system  administrato rs
C. (a) are mandatory  test for  government applications and (b) are  usually  optional
D. (a) are  for  custom-developed  software and (b) are  for  off � the - shelf  software

D is correct
<<<<<< =================== >>>>>>

Q.: Regression testing should be performed:

v) Every week
w) After the software has changed
x) As often as possible
y) When the environment has changed
z) Wwhen the project manager says
A. v & w are true, x � z are false
B. w, x & y are true, v & z are false
C. w & y are true, v, x & z are false

D. w is true, v, x y and z are false

E. All of the above are true
C is correct


<<<<<< =================== >>>>>>
 
Q.: During which test activity could faults be found most cost effectively? 
A. Execution
B. Design

C. Planning
D. Check Exit criteria completion

C is correct
 

<<<<<< =================== >>>>>> 
Q.: What is the difference between testing software developed by contractor outside your country, versus testing software developed by a contractor within your country? 
A. Does not meet people needs
B. Cultural difference

C. Loss of control over reallocation of resources
D. Relinquishments of control

B is correct
<<<<<< =================== >>>>>>
Q.: Consider the following list of test process activities:
I. Analysis and design
II. Test closure activities
III. Evaluating exit criteria and reporting
IV. Planning and control
V. Implementation and execution
Which of the following places these in their logical sequence?
 
A. I, II,
III, IV and V.
B. IV, I, V, III and II.
C. IV, I, V, II and III.
D. I, IV, V, III and II.
B is correct

<<<<<< =================== >>>>>>
Q.: Test objectives vary between projects and so must be stated in the test plan. Which one of the following test objectives might conflict with the proper tester mindset?
A. Show that the system works before we ship it.
B. Find as many defects as possible.
C. Reduce the overall level of product risk.
D. Prevent defects through early involvement.

A is correct
 <<<<<< =================== >>>>>>
Q.: Which test activities are supported by test data preparation tools?
A. Test management and control
B. Test specification and design
C. Test execution and logging
D. Performance and monitoring

B is correct
 

<<<<<< =================== >>>>>>
Q.: Consider the following types of tools: V. Test management tools
W. Static analysis tools
X. Modeling tools
Y. Dynamic analysis tools
Z. Performance testing tools
Which of the following of these tools is most likely to be used by developers?
 

A. W, X and Y
B. V, Y and Z
C. V, W and Z
D. X, Y and Z
A is correct
 

<<<<<< =================== >>>>>> 
Q.: What is a test condition? 
A. An input, expected outcome, pre-condition and post-condition
B. The steps to be taken to get the system to a given point
C. Something that can be tested
D. A specific state of the software, e.g. before a test can be run
C is correct
 

<<<<<< =================== >>>>>>  
Q.: Which  of  the  following  general  testing  principles  are t rue? Testing  shows the  presence of  defects  but  not the  absence of  defects
Testing  of combinations  of  inputs  and  outputs  will find  all  defects
Testing  should start after the  completion  of key  development tasks
Testing  of  safety-critical  software  is  similar to  testing  web  applications
A. I is true; II, III and IV are false
B. II is true; I, III and IV are false
C. I and II are true; III and N are false
D. II and III are true; I and IV are false
A is correct
 

<<<<<< =================== >>>>>> 
 Q.: If the temperature falls below 18 degrees, the heating is switched on. When the temperature reaches 21 degrees, the heating is switched off. What is the minimum set of test input values to cover all valid equivalence partitions?
A. 15, 19 and 25 degrees
B. 17, 18, 20 and 21 degrees
C. 18, 20 and 22 degrees
D. 16 and 26 degrees

A is correct
 

<<<<<< =================== >>>>>> 
 Q.: By  creating  future  tests  based  on the  results  of  previous  tests,  a  tester  is  demonstrating what type  of  informal  test  design  technique? 
A. Security  testing
B. Non-functional  testing
C. Exploratory  testing
D. Interoperability  testing
C is correct
 

<<<<<< =================== >>>>>> 
 Q.: What is the purpose of confirmation testing?  
A. To confirm the users' confidence that the system will meet their business needs.
B. To confirm that a defect has been fixed correctly.
C. To confirm that no unexpected changes have been introduced or uncovered as a result of changes made.
D. To confirm that the detailed logic of a component conforms to its specification.
B is correct
 

<<<<<< =================== >>>>>> 
Q.: Which success factors are required for good tool support within an organization? 
A. Acquiring the best tool and ensuring that all testers use it.
B. Adapting processes to fit with the use of the tool and monitoring tool use and benefits.
C. Setting ambitious objectives for tool benefits and aggressive deadlines for achieving them.
D. Adopting practices from other successful organizations and ensuring that initial ways of using the tool are maintained.
B is correct
<<<<<< =================== >>>>>>
 


 


No comments:

Post a Comment

To bring all feasible courses , online and easy to use...